Week commencing 19th January 2026

Plenty going on during week commencing 12th January 2026, across multiple fronts.

  • Monday sees ducting work underway in offices 12A, 15 and the breakout room.  There’ll be low to no noise expected.
  • On Tuesday and Wednesday mornings, first thing, there’ll be a bit of drilling in those three offices, but this should be concluded by 9am.  Work will then continue on Friday.
  • Work on the front offices above the cafe will continue through the week, with noise expected to be minimal.
  • Exterior landscaping works will continue through the week.

 